Free demo of Production Planning & Manufacturing with SAP ERP 6.0 EHP7 C_TSCM42_67 exam is available for you so just click and get the instant download of both these products moreover you can make the MacAfee Secure payment to get the best SAP Certified Application Associate – Production Planning & Manufacturing with SAP ERP 6.0 EHP7 C_TSCM42_67 exam dumps material within very short time. Do not wait for the trainer to evaluate your learning but do it yourself with practice test software because self-assessment feature is included in SAP Certified Application Associate – Production Planning & Manufacturing with SAP ERP 6.0 EHP7 C_TSCM42_67 exam.

♥ VALID C_TSCM42_67 Exam Questions 2018 ♥

C_TSCM42_67 exam questions, C_TSCM42_67 PDF dumps; C_TSCM42_67 exam dumps:: https://www.dumpsschool.com/C_TSCM42_67-exam-dumps.html (160 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest SAP C_TSCM42_67 Dumps Exam Questions and Answers:

Version: 5.0
Question: 1

You want to use the different options for planning in SAP ECC. What is the correct sequence of the
planning procedures?
Please choose the correct answer.
Response:

A. Sales and operations planning -> Demand management -> Long-term planning -> Material
requirements planning -> Capacity planning
B. Demand management -> Sales and operations planning -> Capacity planning -> Long-term
planning -> Material requirements planning
C. Material requirements planning -> Demand management -> Sales and operations planning ->
Long-term planning -> Capacity planning
D. Long-term planning -> Sales and operations planning -> Demand management -> Material
requirements planning -> Capacity planning

Answer: A

Question: 2

You want to use production/resource tools in your manufacturing process. Which production type do
you use?
Please choose the correct answer.
Response:

A. Repetitive manufacturing
B. Production order
C. Process order
D. KANBAN

Answer: B

Question: 3

For which of the following objects can you enter a confirmation?
There are 2 correct answers to this question.
Response:

A. Production order
B. Production order operation
C. Trigger Point
D. Work Center

Answer: AB

Question: 4

Which of the following master data can be used with process orders?
There are 3 correct answers to this question.
Response:

A. Serial numbers
B. Master recipes
C. Resources
D. Production/resource tools
E. Production versions

Answer: BCE

Question: 5

You want to use the function “Read PP master data” in the production order. However, while calling
the function you receive an error message. What could be the reason?
Please choose the correct answer.
Response:

A. The material availability check has been performed.
B. Goods movements have been posted.
C. The production order has been released.
D. Order papers have been printed.

Answer: B

Question: 6

How can you convert planned orders into production orders in an SAP ECC system?
There are 3 correct answers to this question.
Response:

A. Automatically, in the planning run (MRP)
B. Set the conversion indicator in Customizing for the planned order.
C. Use mass processing.
D. Use the order progress report.
E. Use background processing.

Answer: CDE

New Updated C_TSCM42_67 Exam Questions C_TSCM42_67 PDF dumps C_TSCM42_67 practice exam dumps: https://www.dumpsschool.com/C_TSCM42_67-exam-dumps.html